Scheme wise Financial Summary
As on 22-12-2024 11:56
S.No. | Scheme Name | Total Allocation (Cr.) | DAPSC Allocation (Cr.) | % DAPSC Allocation w.r.t. Total Allocation | Revised Allocation (Cr.) | % Revised Allocation w.r.t. Total Allocation | Expenditure (Cr.) | % Expenditure w.r.t. Revised Allocation |
---|---|---|---|---|---|---|---|---|
1 |
Kisan Urja Suraksha evam Utthaan Mahabhiyan (KUSUM) » Programme Component |
1996.46 | 201 | 10.07 % | 51.67 | 2.59 % | 60.231 | 116.57 % |
2 |
Solar Power (Grid) » Programme Component |
4970 | 428 | 8.61 % | 409.67 | 8.24 % | 172.7257 | 42.16 % |
3 |
Wind Power (Grid) » Programme Component |
1214 | 130 | 10.71 % | 115.13 | 9.48 % | 115.129 | 100 % |
4 | Green Energy Corridor | 500 | 40 | 8 % | 40 | 8 % | 40 | 100 % |
Total | 8680.46 | 799 | 9.2 % | 616.47 | 7.1 % | 388.0857 | 62.95 % |